Construction work to prepare Otago's Corrections Facility for the transfer of high-security prisoners from Christchurch,  has been delayed
	Construction work to prepare Otago's Corrections Facility for the transfer of high-security prisoners from Christchurch,  has been delayed
    
	
    
	
	13 May 2022 
		
		
        
	
Global supply chain issues and material shortages has pushed the timeline for completion from May to late June.
The transfers were originally due to be completed by mid-September last year, but were delayed to allow time for the renovations.
Additional security features are being added to the unit, where the men will be moved to.
The estimated cost of the construction work is 1.6 million dollars.
	